Are you planning a construction or renovation project? Here you can find information about the required permits, applying instructions and contact details to Building Control.
A building permit must be applied in accordance with Section 42 of the Building Act. The permit should be applied for well in advance of starting the buidling project or renovation project.
The permit is usually processed within 2–4 weeks after all required documents and reports have been submitted to Building Control. A building permit is valid for five years, and construction must be started within three years after the permit has been granted.
Fees for building and other permits are charged according to the current price list. A separate fee is charged for processing paper applications.
Building must comply with applicable legislation, building regulations and decrees, the local detailed plan and the building ordinance.
Learn about building permits and supervision
A building permit is required for most construction projects as well as significant repair and alteration works.
Demolition permit / Demolition notification
Demolition of a building often requires a permit or a notification to Building Control.
A deviation permit is required if the construction seeks to deviate from the plan or other land use regulations.
A siting permit is a separate permit that assesses the placement of the building on the plot before construction.
A landscape work permit is required, for example, for tree felling or ground modification works in certain areas.
Inspections related to construction ensure that the work proceeds in accordance with the permit decision and that the requirements are met at the different stages.
Supervision of the built environment
Building Control supervises that construction and the use of buildings comply with applicable laws, regulations and permits.